PERMIT REQUIREMENTS:
-
"SDRF" TO BE BILLED
TOTAL SQ. FT. = 0.00SQ. FT.
TOTAL SDRF FEE = = $0.00
-
"SSDRF" TO BE BILLED
TOTAL SSDRF SQ. FT. =
0
SQ. FT.
TOTAL SSDRF FEE = = $0.00
-
"SDRF/SSDRF Administration Fee" TO BE BILLED
TOTAL SDRF ADMINISTRATION FEE = = $0.00
TRAFFIC CONTROL CONDITIONS
- WATCH MANUAL: TRAFFIC CONTROL SETUP SHALL BE PER THE WATCH MANUAL CONDITIONS (2019 EDITION) AND MANUAL OF UNIFORM TRAFFIC CONTROL DEVICES (MUTCD 2009).
- STREET ACCESS: MAINTAIN LOCAL AND EMERGENCY ACCESS ON ALL STREETS.
- MAINTAIN ACCESS TO ALL DRIVEWAYS, SIDEWALKS, AND CROSSWALKS AT ALL TIMES.
SPECIAL PERMIT REQUIREMENTS:
Trench backfill and a/c pavement resurfacing shall follow the
latest version of la city std plan s-477-2. One sack slurry within street. 1.5
sack slurry or one sack slurry with in-kind compacted base material in concrete
streets/sidewalk. Native soil backfill in landscape and dirt.
Damaged
concrete is to be restored in kind to the nearest built scoreline. Affected
landscaping is to be restored in kind. Contractor shall be responsible for the
protection of public and private property adjacent to the work and shall
exercise due caution to avoid damage to such property.
Whenever a
sidewalk or curb is removed and replaced to accommodate a utility installation,
any and all survey monuments must be preserved or replaced by the utility or
their contractor. The contractor shall repair or replace “in-kind” all existing
improvements within the right-of-way which are not designated for removal
(e.g., curbs, sidewalks, driveways, fences, walls, signs, installations,
pavements, structures, etc.) Which are damaged or removed as a result of its
operations.