APPLICANT |
DWP-Water , Harbor District
|
CITY |
ZIP |
TELEPHONE |
San Pedro
|
90731
|
|
REQUEST PREPARED BY |
TELEPHONE |
Marlo Abantao
|
3104648404
|
ALL WORK MUST BE DONE IN
ACCORDANCE WITH THE LATEST ADOPTED EDITION & SUPPLEMENTS OF THE STANDARD
SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION, THE LATEST REVISION OF THE BROWN BOOK,
AND THE WORK AREA TRAFFIC CONTROL HANDBOOK (WATCH MANUAL).
|
Grape Street and 101st Street
Los Angeles, CA 90002
|
Installation of approximately 1,177 LF of 8" watermain and associated services along Lou Dillon Avenue (north of 101st Street) including necessary water meters to service the properties. This work is considered "Per Paid Order".
|
Permit Cuts:
No. |
L x W x D |
On Street |
Cross Street |
SDRF Sq Ft |
SDRF Fee |
Surface |
Backfill |
3 |
1.49 (ft)
x 1.67 (ft)
x 4.00 (ft)
|
GRAPE |
CENTURY |
109.26 |
$900.34 |
Street Asphalt Concrete |
Slurry |
5 |
256.22 (ft)
x 1.67 (ft)
x 4.00 (ft)
|
GRAPE |
CENTURY |
2,531.59 |
$20,860.32 |
Street Asphalt Concrete |
CLSM |
10 |
1.48 (ft)
x 1.67 (ft)
x 4.00 (ft)
|
GRAPE |
101ST |
109.17 |
$899.53 |
Street Asphalt Concrete |
CLSM |
18 |
7.07 (ft)
x 1.67 (ft)
x 4.00 (ft)
|
101ST |
GRAPE |
162.33 |
$1,337.58 |
Street Asphalt Concrete |
CLSM |
20 |
7.07 (ft)
x 1.67 (ft)
x 4.00 (ft)
|
101ST |
GRAPE |
162.33 |
$1,337.58 |
Street Asphalt Concrete |
CLSM |
21 |
83.40 (ft)
x 1.67 (ft)
x 4.00 (ft)
|
101ST |
GRAPE |
888.18 |
$7,318.59 |
Street Asphalt Concrete |
CLSM |
23 |
22.66 (ft)
x 1.67 (ft)
x 4.00 (ft)
|
101ST |
LOU-DILLON |
310.57 |
$2,559.14 |
Street Asphalt Concrete |
CLSM |
24 |
25.32 (ft)
x 1.67 (ft)
x 4.00 (ft)
|
101ST |
LOU-DILLON |
335.87 |
$2,767.55 |
Street Asphalt Concrete |
Slurry |
25 |
460.93 (ft)
x 1.67 (ft)
x 4.00 (ft)
|
101ST |
GRAPE |
4,478.26 |
$36,900.83 |
Street Asphalt Concrete |
CLSM |
29 |
1.50 (ft)
x 25.45 (ft)
x 4.00 (ft)
|
101ST |
GRAPE |
332.20 |
$2,737.34 |
Street Asphalt Concrete |
CLSM |
31 |
1.50 (ft)
x 1.67 (ft)
x 4.00 (ft)
|
101ST |
LOU-DILLON |
109.36 |
$901.14 |
Street Asphalt Concrete |
CLSM |
35 |
49.00 (ft)
x 1.67 (ft)
x 4.00 (ft)
|
GRAPE |
101ST |
561.05 |
$4,623.09 |
Street Asphalt Concrete |
CLSM |
36 |
21.13 (ft)
x 1.67 (ft)
x 4.00 (ft)
|
GRAPE |
101ST |
296.03 |
$2,439.29 |
Street Asphalt Concrete |
CLSM |
37 |
75.00 (ft)
x 1.67 (ft)
x 4.00 (ft)
|
101ST |
GRAPE |
808.30 |
$6,660.38 |
Street Asphalt Concrete |
CLSM |
39 |
1.50 (ft)
x 27.45 (ft)
x 4.00 (ft)
|
101ST |
GRAPE |
350.94 |
$2,891.77 |
Street Asphalt Concrete |
CLSM |
43 |
1.67 (ft)
x 11.00 (ft)
x 4.00 (ft)
|
GRAPE |
CENTURY |
199.70 |
$1,645.51 |
Street Asphalt Concrete |
CLSM |
44 |
1.67 (ft)
x 29.10 (ft)
x 4.00 (ft)
|
GRAPE |
CENTURY |
371.82 |
$3,063.79 |
Street Asphalt Concrete |
CLSM |
48 |
1.67 (ft)
x 11.00 (ft)
x 4.00 (ft)
|
GRAPE |
CENTURY |
199.70 |
$1,645.51 |
Street Asphalt Concrete |
CLSM |
49 |
1.67 (ft)
x 11.00 (ft)
x 4.00 (ft)
|
GRAPE |
CENTURY |
199.70 |
$1,645.51 |
Street Asphalt Concrete |
CLSM |
50 |
1.67 (ft)
x 29.10 (ft)
x 4.00 (ft)
|
GRAPE |
101ST |
371.82 |
$3,063.79 |
Street Asphalt Concrete |
CLSM |
51 |
1.50 (ft)
x 7.00 (ft)
x 4.00 (ft)
|
101ST |
GRAPE |
159.30 |
$1,312.67 |
Street Asphalt Concrete |
CLSM |
52 |
1.50 (ft)
x 31.13 (ft)
x 4.00 (ft)
|
101ST |
GRAPE |
385.42 |
$3,175.86 |
Street Asphalt Concrete |
CLSM |
53 |
1.50 (ft)
x 44.14 (ft)
x 4.00 (ft)
|
101ST |
LOU-DILLON |
507.34 |
$4,180.47 |
Street Asphalt Concrete |
CLSM |
54 |
1.50 (ft)
x 7.00 (ft)
x 4.00 (ft)
|
101ST |
LOU-DILLON |
159.30 |
$1,312.67 |
Street Asphalt Concrete |
CLSM |
55 |
1.50 (ft)
x 5.00 (ft)
x 4.00 (ft)
|
101ST |
LOU-DILLON |
140.56 |
$1,158.24 |
Street Asphalt Concrete |
CLSM |
IS THIS WORK RELATED TO A CITY NOTICE OF PROPOSED IMPROVEMENT?
|
|
IS STREET NOW UNDER CONSTRUCTION?
|
|
Greater than 1000 sq. ft.
|
ISSUED BY:
Chinh Dinh
|
Reference Number |
2022010094 |
Permit Number |
U-2250-4363
|
W.O. NO. |
UR601134
|
Date Issued |
09/30/2022
|
Date Expires |
08/28/2023
|
Work to be Completed by: |
06/30/2023
|
Permit Tag(s) |
|
|
JOB Sq. Ft. |
2,063.55
|
ITEM |
QUANTITY |
UNIT |
RATE |
FEE $ |
U-Permit Excavation <= 1,000 |
1
|
EA
|
$191.00
|
$0.00
|
U-Permit Special Eng Fee |
0.0
|
Hrs
|
$149.00
|
$0.00
|
Special Inspec. Fee |
0.0
|
Hrs
|
$95.00
|
$0.00
|
Overtime Inspec. Fee |
0.0
|
Hrs
|
$95.00
|
$0.00
|
Inspection
|
2,063.55
|
SQ FT
|
Cost
|
Cost
|
BSS Peak Hr. Comp.Fee |
Local Std (Local Street)
|
EA
|
$0.00
|
$0.00
|
LADOT Peak Hr. Comp.Fee |
Local Std (Local Street)
|
EA
|
$0.00
|
$0.00
|
Street Damage |
14,240.11
|
Sq. Ft.
|
|
$117,338.49
|
SDRF Admin. Fee |
1
|
EA
|
$18.50
|
$18.50
|
SDRF Admin. Surcharge |
1
|
EA
|
|
$2.30
|
CONST MGMT TRAFFIC FEE |
0 Lanes
|
0 Days
|
|
$0.00 |
Dev Srvc Sur (3.0000%)-Min $1 |
|
|
3.00% |
$0.00
|
Equip & Training Sur (7%)-Min $1 |
|
|
7%
|
$0.00
|
TOTAL FEE
|
$117,359.29
|
JOB NO. |
|
DRAWING NO. |
|
ACCOUNT NO. |
|
U.S.A. NO. |
|
LOCATOR CODE |
|
THOMAS GUIDE PAGE |
704:4:H
|
Inspection ID/Conf. No |
354928
|
Inspection Date |
6/9/2023 9:00:00 AM
|
Inspection Status
|
Not Finalized
|
MUST CALL FOR INSPECTION : (213)485-5080
BEFORE, DURING, AND AFTER CONSTRUCTION
|
|