-
Three (3) sets of plans, two (2) sets of
structural calculations, and two (2) sets of Soils and Geology Report are
required for structural review.
-
A Soils and Geology report must be approved by
the Geotechnical Services Section of the Bureau of Engineering, prior to our
structural review.
-
Resubmit originally checked plans/calculations
with corrected plans/calculations.
-
Plans/Calculations must be stamped and signed by
a licensed Civil or Structural Engineer.
-
Conditions of approval contained in the Soil and
Geology report must be indicated on the plans.
-
Provide material specifications for
concrete/steel/wood/masonry/design data.
-
Provide a Complete E-Permit’s job title and
work order number on all correspondence.
-
Provide the complete job title/sheet number/work
order number on the plans.
- Show all details on City Standard Sheets.
-
Show all pertinent structural notes on the
plans.
-
Show all structural design criteria on the
plans.
© 1999-2025 Bureau of Engineering
Department of Public Works, City of Los Angeles. Version 1.0
